Kwang Yang Viet Nam Co., Ltd. Factory and Warehouse

Construction site: Dai Dang Industrial Park, Thu Dau Mot, Binh Duong. Construction works: Factory, Officem Parking lot, Canteen, Internal Road, Drainage system. Total construction area: 50.000 m2

Painting workshop:  3,015 m2

Office building – Assembly workshop: 17,676 m2

Fence type A & B: Diện tích 950m2

Guardhouse: 36m2

Gate – signs – flag post: 23.4 m2

2-wheeled parking lot: 700m2

Development room: 550.8 m2

Power station, scrap storage: 485 m2

Heavy-weight road: 5,083 m2

Light-weight road: 9,210 m2

Test driving road: 2,863 m2

Waste water treatment tank: 250.2 m2

Fire-prevention tank: 108 m2

Restroom areas (5 areas): 148.5 m2

Rain water drainage system: 1.471 m2

Waste water drainage system: 922 m2

Canteen: Diện tích 2,432.68 m2

Floating roof: 162 m2